111 MW Barossa BESS
Critical emergency response after a fault on the 275 kV incoming cable. Given four days' notice, we designed a switching program to isolate the site, take the main transformer offline for its service window and re-energise the full BESS across a two-day coordinated operation.


Outcome
Site safely isolated, service window completed, re-energised without incident.
Services on this job
Capabilities
Enquiry
Tell us the voltage, the asset and the window.