We terminate and joint high voltage cables. We work on substations and switchgear. We do the work most electricians can't.

Earthed started in the Adelaide Hills, founded by Caleb Vears in 2024 off the back of ten years working in distribution power systems with a strong focus on renewable energy. Since then Earthed has worked alongside some of the world's leading renewable energy companies, right here in South Australia. We hold a real focus on maintaining a healthy working environment, using our craft to implement strict safe operating procedures inside our in-house safety system. Our clients get the confidence of knowing Earthed was there.

Find out about our project success below, and let us know if we can assist you in the world of green energy.

Earthed has worked alongside large international companies, local and non-local investors and local network connection expertise. We welcome any enquiry for collaboration.

Earthed High Voltage vehicle beside a row of battery containers
On a battery site in South Australia.

Practice

One founder. The work in front of him.

Caleb Vears founded Earthed High Voltage Pty Ltd in 2024. The company holds SA electrical contractor licence PGE 336477. ABN 99 679 180 879. ACN 679 180 879.

The safety system is in-house: safe operating procedures, switching sheets, permits and an ePermit. Clients get the confidence of knowing Earthed was there.

  1. 2024

    Founded in the Adelaide Hills

    Caleb Vears started Earthed after ten years in distribution power systems, with the work pointed at renewable energy.

  2. Wind

    Goyder South

    Specialist jointing partner across the whole site. 78 turbines connected. The project that shaped Earthed's technical direction.

  3. Solar

    Port Wakefield

    First EPC site. Handed over in 16 weeks: grid-connected, commissioned and operational.

  4. Repair

    Kerta Road

    Sixteen 300 mm² cables severed mid-build. Sixteen joints, IR and VLF tested, asset returned to service.

  5. Battery

    Barossa and Tailem Bend

    A two-day switching operation on the 111 MW Barossa BESS, and ongoing O+M on the live Tailem Bend battery.